Filter Pencarian SubSLS
Daftar Rincian SubSLS (Blok Sensus)
(22 / 22 SubSLS)
| No | Nama SLS | Wilayah | Petugas (PCL/PML/Korlap) | Status | FASIH % | Muatan % | Assignment FASIH | Progres Muatan | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Open | Draft | Submitted | Approved | Rejected | Target | Realisasi | Target | Usaha Baru | |||||||
| 1 |
Sepaku
Tengin Baru
|
Sedang Didata |
98.97%
96 / 97
|
94.68%
89 / 94
|
0 | 0 | 0 | 96 | 0 | 97 | 89 | 94 | +6 | ||
| 2 |
Sepaku
Tengin Baru
|
Sedang Didata |
92.86%
52 / 56
|
18.46%
12 / 65
|
0 | 0 | 12 | 40 | 0 | 56 | 12 | 65 | +0 | ||
| 3 |
Sepaku
Tengin Baru
|
Sedang Didata |
52.17%
36 / 69
|
35.11%
33 / 94
|
0 | 0 | 3 | 33 | 0 | 69 | 33 | 94 | +0 | ||
| 4 |
Sepaku
Tengin Baru
|
Melebihi Target |
100.00%
217 / 217
|
106.93%
216 / 202
|
0 | 0 | 0 | 217 | 0 | 217 | 216 | 202 | +29 | ||
| 5 |
Sepaku
Tengin Baru
|
Melebihi Target |
100.00%
202 / 202
|
102.02%
202 / 198
|
0 | 0 | 2 | 200 | 0 | 202 | 202 | 198 | +35 | ||
| 6 |
Sepaku
Tengin Baru
|
Sedang Didata |
64.00%
64 / 100
|
56.31%
58 / 103
|
0 | 2 | 5 | 59 | 0 | 100 | 58 | 103 | +7 | ||
| 7 |
Sepaku
Tengin Baru
|
Sedang Didata |
30.48%
32 / 105
|
26.02%
32 / 123
|
0 | 0 | 0 | 32 | 0 | 105 | 32 | 123 | +0 | ||
| 8 |
Sepaku
Tengin Baru
|
Sedang Didata |
30.38%
24 / 79
|
23.76%
24 / 101
|
0 | 0 | 0 | 24 | 0 | 79 | 24 | 101 | +0 | ||
| 9 |
Sepaku
Tengin Baru
|
Sedang Didata |
42.11%
16 / 38
|
25.45%
14 / 55
|
0 | 1 | 2 | 14 | 0 | 38 | 14 | 55 | +0 | ||
| 10 |
Sepaku
Tengin Baru
|
Sedang Didata |
92.06%
58 / 63
|
58.62%
34 / 58
|
0 | 4 | 8 | 50 | 0 | 63 | 34 | 58 | +1 | ||
| 11 |
Sepaku
Tengin Baru
|
Melebihi Target |
96.30%
52 / 54
|
108.33%
52 / 48
|
0 | 2 | 0 | 52 | 0 | 54 | 52 | 48 | +12 | ||
| 12 |
Sepaku
Tengin Baru
|
Melebihi Target |
92.31%
168 / 182
|
143.33%
172 / 120
|
0 | 14 | 3 | 165 | 0 | 182 | 172 | 120 | +42 | ||
| 13 |
Sepaku
Tengin Baru
|
Sedang Didata |
90.24%
148 / 164
|
89.61%
138 / 154
|
0 | 6 | 29 | 119 | 0 | 164 | 138 | 154 | +20 | ||
| 14 |
Sepaku
Tengin Baru
|
Sedang Didata |
98.32%
117 / 119
|
83.48%
96 / 115
|
0 | 2 | 10 | 107 | 0 | 119 | 96 | 115 | +12 | ||
| 15 |
Sepaku
Tengin Baru
|
Sedang Didata |
100.00%
82 / 82
|
92.13%
82 / 89
|
0 | 0 | 0 | 82 | 0 | 82 | 82 | 89 | +12 | ||
| 16 |
Sepaku
Tengin Baru
|
Sedang Didata |
41.46%
51 / 123
|
9.03%
13 / 144
|
0 | 22 | 38 | 13 | 0 | 123 | 13 | 144 | +0 | ||
| 17 |
Sepaku
Tengin Baru
|
Sedang Didata |
99.54%
217 / 218
|
82.51%
217 / 263
|
0 | 0 | 0 | 217 | 0 | 218 | 217 | 263 | +32 | ||
| 18 |
Sepaku
Tengin Baru
|
Sedang Didata |
100.00%
91 / 91
|
68.04%
66 / 97
|
0 | 0 | 0 | 91 | 0 | 91 | 66 | 97 | +9 | ||
| 19 |
Sepaku
Tengin Baru
|
Sedang Didata |
22.68%
22 / 97
|
13.58%
22 / 162
|
0 | 1 | 0 | 22 | 0 | 97 | 22 | 162 | +0 | ||
| 20 |
Sepaku
Tengin Baru
|
Sedang Didata |
100.00%
73 / 73
|
88.89%
72 / 81
|
0 | 0 | 0 | 73 | 0 | 73 | 72 | 81 | +9 | ||
| 21 |
Sepaku
Tengin Baru
|
Sedang Didata |
100.00%
64 / 64
|
84.21%
64 / 76
|
0 | 0 | 0 | 64 | 0 | 64 | 64 | 76 | +6 | ||
| 22 |
Sepaku
Tengin Baru
|
Sedang Didata |
97.95%
143 / 146
|
89.26%
108 / 121
|
0 | 3 | 1 | 142 | 0 | 146 | 108 | 121 | +24 | ||
Rincian SubSLS
RT 007 DUSUN II TEGAL MULYO
6409040009000700
Kecamatan
Sepaku
Desa/Kelurahan
Tengin Baru
Pencacah (PCL)
Arifin Ilham
Pengawas (PML)
Kaharuddin
Korlap
Yamin
Status Progres SLS:
Sedang Didata
Assignment FASIH
30.48%
Open
0
Draft
0
Submit
0
Appr
32
Rejc
0
Progres Muatan
26.02%
Temuan Keberadaan Usaha
0
0
2
2
28
Temuan Keberadaan Keluarga
Ditemukan
0
Klg Baru
0
Tdk Ada
0
Analisis Kecepatan & Sisa Waktu
Kecepatan Saat Ini
0.52 dok/hari
Status Target
Off-Track
Hari berjalan pendataan: 62 hari (sejak 15 Juni 2026). Sisa hari menuju deadline (17 Agustus 2026): 2 hari.
Sisa beban kerja: 73 dokumen. Dengan kecepatan saat ini (0.52 dok/hari), beban kerja diprediksi akan selesai dalam waktu sekitar 142 hari.
Sisa beban kerja: 73 dokumen. Dengan kecepatan saat ini (0.52 dok/hari), beban kerja diprediksi akan selesai dalam waktu sekitar 142 hari.
Off-Track: Progres diprediksi terlambat/tidak selesai tepat waktu. Diperlukan peningkatan kecepatan kerja minimal menjadi 36.50 dok/hari agar selesai sesuai target pada 17 Agustus 2026.
Tren Progres Harian (FASIH)